Profiles of Turkish Public Sector Projects for Foreign Funding in 2000 Energy
...
ALPASLAN DAM AND HEPP (I ,II)
1991D020070
...
Project Description 160 MW (ALPASLAN I), 488 GWh
200 MW (ALPASLAN II), 714 GWh
Executing Agency Gen. Dir. of State Hydraulic Works (DSÝ)
Location Muþ
Duration 1991 - 2002
Status The project is located in Euphrates Basin. Under this project title, there are two HEPP projects; 
namely Alpaslan I, and Alpaslan II.  In Alpaslan I, the final design of the project is completed. 
Civil works are still in progress. The power plant is expected to be commissioned in 2001. 
Foreign financing is needed for the supply of electro-mechanical equipment and relevant 
contract is scheduled to be awarded in 2000.  As for the Alpaslan II, the feasibility study 
of the project has been completed.  Project is to be realized within the Turkish-American protocol.
...
(million US$)
Foreign
TOTAL
Project Cost 
95,0
532,0
Accumulated Expenses as of End 1999
0,0
120,0
2000 Allocation
0,0
31,0
Required Loan Amount
95,0