Profiles of Turkish Public Sector Projects for Foreign Funding in 2000 Manufacturing
...
ESKİŞEHİR SPRING WATER BOTTLING PLANT  1995C020040
...
Project Description Modernization of transmission line and bottling plant
Executing Agency Gen. Dir. of Eskişehir Water and Sewerage Administration
Location Eskişehir
Duration 1995 - 2001
Status Eskişehir Municipality is executing an integrated modernization project 
concerning the water system of Eskişehir. This project is a sub-project of the
modernization project and related with the renewal of the 
Türkmendağı-Eskişehir transmission line and renewal of the bottling plant fed
by this line.
Plastic bottle filling machines for bottles of 1 lt., 2 lt. and 3 lt., together with 
polycarbonate bottle production and filling machines for bottles of 12 lt. and 19 
lt. is added to the plant with the project. After implementing the project, plant 
will have an additional production capacity of 1.275.000 lt. per day.
Transmission line which carries Kalabak spring water will be enlarged to 40 lt
...
(million US$)
Foreign
TOTAL
Project Cost 
 15,0
 15,0
Accumulated Expenses as of End 1999
 0,0
 0,0
2000 Allocation
 10,0
 10,0
Required Loan Amount
 15,0