ADNAN MENDERES AIRPORT NEW TERMINAL BUILDING  
...
Project Description Construction of International Lines Terminal Building
Executing Agency Gen.Dir.of State Airports Administration (DHMĘ)
Location Ęzmir
Duration
Status
 
 
 
 
 
The capacity of terminal building is planned to be 5 million passenger per
annum. Total area of terminal is 102.000 m2. In the range of the project there
are 2200 car-capacity car-park area, 9 passenger bridges, 60 check-in 
counters, passport control counters and commercial volumes.
International tender by BOT model was opened on 06.02.1999 and proposals
will be taken till 05.04.2000. The tender will be realized at the same day.
...
(million US$)
Foreign
TOTAL
Project Cost 
0,0
90,0
Accumulated Expenses as of End 1999
0,0
0,0
2000 Allocation
0,0
0,0
Required Loan Amount
0,0